Non payment in the construction industry
(Created page with "Introduction Non-payment in construction can also be referred to as withholding payment. This can be due to a dispute or contractual breach between two parties for non-performan...") |
|||
Line 1: | Line 1: | ||
− | Introduction | + | = Introduction = |
Non-payment in construction can also be referred to as withholding payment. This can be due to a dispute or contractual breach between two parties for non-performance of a certain clause. Provided that a party to a contract issues a compliant withholding-notice setting out the grounds and the sums attributable to each ground, then the party may legitimately withhold payment. The Housing Act will take precedence over any client payment clauses and will need to be adhered to. | Non-payment in construction can also be referred to as withholding payment. This can be due to a dispute or contractual breach between two parties for non-performance of a certain clause. Provided that a party to a contract issues a compliant withholding-notice setting out the grounds and the sums attributable to each ground, then the party may legitimately withhold payment. The Housing Act will take precedence over any client payment clauses and will need to be adhered to. | ||
− | The Housing Act guidelines to adhere to prior to withholding payment | + | = The Housing Act guidelines to adhere to prior to withholding payment = |
Payment in Construction will be subject to [https://www.designingbuildings.co.uk/wiki/The_Housing_Grants,_Construction_and_Regeneration_Act The Housing Grants Act] 1996 (also known as the Construction Act) To issue a valid withhold notice or for nonpayment to be legitimate, it cannot conflict with the following stipulations: | Payment in Construction will be subject to [https://www.designingbuildings.co.uk/wiki/The_Housing_Grants,_Construction_and_Regeneration_Act The Housing Grants Act] 1996 (also known as the Construction Act) To issue a valid withhold notice or for nonpayment to be legitimate, it cannot conflict with the following stipulations: | ||
Line 19: | Line 19: | ||
* Impose a limit of not more than 30 calendar days (before the payment period begins) for the purchaser to verify the conformity of goods/services are in accordance with the contract - but this period can be exceeded by agreement and provided it is not grossly unfair to the supplier. | * Impose a limit of not more than 30 calendar days (before the payment period begins) for the purchaser to verify the conformity of goods/services are in accordance with the contract - but this period can be exceeded by agreement and provided it is not grossly unfair to the supplier. | ||
− | Grounds for Non payment | + | = Grounds for Non payment = |
To withhold payment the following grounds must be met as a minimum: | To withhold payment the following grounds must be met as a minimum: | ||
Line 34: | Line 34: | ||
When drafting a withholding notice, it is important to set out the grounds and the amount attributable to each ground. | When drafting a withholding notice, it is important to set out the grounds and the amount attributable to each ground. | ||
− | JCT and NEC compared | + | = JCT and NEC compared = |
There are significant differences in the timescales for withholding payment in JCT and NEC Contracts. Each contract sets out their own payment due dates. As a general guide, the JCT stipulates that a withholding notice will need to be issued at least 5 days in advance of the final date for payment. The NEC has a longer period of 7 days. These dates however will be specific to each contract and will have to be adhered to for a valid non-payment/withholding-notice to be issued. | There are significant differences in the timescales for withholding payment in JCT and NEC Contracts. Each contract sets out their own payment due dates. As a general guide, the JCT stipulates that a withholding notice will need to be issued at least 5 days in advance of the final date for payment. The NEC has a longer period of 7 days. These dates however will be specific to each contract and will have to be adhered to for a valid non-payment/withholding-notice to be issued. | ||
− | Conclusion | + | = Conclusion = |
The non-payment/withholding-notice in construction has to meet several legislative and contractual points to be valid. Contractors are within their rights to suspend performance for non-payment so due diligence will need to be carried out by both parties to avoid disputes and disruption to the construction project. | The non-payment/withholding-notice in construction has to meet several legislative and contractual points to be valid. Contractors are within their rights to suspend performance for non-payment so due diligence will need to be carried out by both parties to avoid disputes and disruption to the construction project. | ||
− | Related articles | + | = Related articles = |
* [https://www.designingbuildings.co.uk/wiki/Causes_of_construction_disputes Causes of construction disputes]. | * [https://www.designingbuildings.co.uk/wiki/Causes_of_construction_disputes Causes of construction disputes]. |
Revision as of 09:30, 3 March 2020
Contents |
Introduction
Non-payment in construction can also be referred to as withholding payment. This can be due to a dispute or contractual breach between two parties for non-performance of a certain clause. Provided that a party to a contract issues a compliant withholding-notice setting out the grounds and the sums attributable to each ground, then the party may legitimately withhold payment. The Housing Act will take precedence over any client payment clauses and will need to be adhered to.
The Housing Act guidelines to adhere to prior to withholding payment
Payment in Construction will be subject to The Housing Grants Act 1996 (also known as the Construction Act) To issue a valid withhold notice or for nonpayment to be legitimate, it cannot conflict with the following stipulations:
- The right to be paid in interim, periodic or stage payments
- The right to suspend (or part suspend) performance for non-payment and to claim cost and expenses incurred and extension of time resulting from the suspension.
- The client must issue a payment notice within five days of the date for payment , even if no amount is due. Alternatively, if the contract allows, the contractor may make an application for payment, which is treated as if it is the payment notice
- The client must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation.
- The notified sum is payable by the final date for payment.
- If the client (or specified person) fails to issue a payment notice, the contractor may issue a default payment notice. The final date for payment is extended by the period between when the client should have issued a payment notice and when the contractor issued the default payment notice. If the client does not issue a payless notice, they must pay the amount in the default payment notice.
- Pay when certified clauses are not allowed, and the release of retention cannot be prevented by conditions within another contract.
The Regulations also:
- Impose a limit of not more than 30 calendar days (before the payment period begins) for the purchaser to verify the conformity of goods/services are in accordance with the contract - but this period can be exceeded by agreement and provided it is not grossly unfair to the supplier.
Grounds for Non payment
To withhold payment the following grounds must be met as a minimum:
- The notice to withhold must be compliant with the contractual requirements.
- The notice to withhold must be compliant with the timing requirements of the contract.
- The notice to withhold must be compliant with the means of issue? (e.g. recorded delivery post)
- The cause (breach) of the contract giving entitlement to withhold must be stated.
- Is there a loss naturally flowing from that breach?
- Is the valuation of the withholding prepared correctly and/or in accordance with the contract?
When drafting a withholding notice, it is important to set out the grounds and the amount attributable to each ground.
JCT and NEC compared
There are significant differences in the timescales for withholding payment in JCT and NEC Contracts. Each contract sets out their own payment due dates. As a general guide, the JCT stipulates that a withholding notice will need to be issued at least 5 days in advance of the final date for payment. The NEC has a longer period of 7 days. These dates however will be specific to each contract and will have to be adhered to for a valid non-payment/withholding-notice to be issued.
Conclusion
The non-payment/withholding-notice in construction has to meet several legislative and contractual points to be valid. Contractors are within their rights to suspend performance for non-payment so due diligence will need to be carried out by both parties to avoid disputes and disruption to the construction project.
Related articles
- Causes of construction disputes.
- Fair payment practices.
- Housing Grants, Construction and Regeneration Act.
- The Late Payment of Commercial Debts Regulations 2013.
- Payment notice.
- Payments to nominated sub-contractors.
- Pay less notice.
- Payment.
- Payment schedule.
- Prompt payment code.
- The causes of late payment in construction.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.