Construction management: tender trade contracts
(Created page with "Tendering is the process of selecting and appointing the trade contractors to construct the works for the main contract. We describe this stage as 'tender' rather than 'tender do...") |
|||
Line 1: | Line 1: | ||
− | + | The tender stage (equivalent to RIBA stage G: tender documentation and H: tender action) is the process of selecting and appointing the contractor for the main contract. We describe this stage as 'tender' rather than 'tender documentation' and 'tender action' (RIBA plan of work) to avoid the proliferation of work stages. We include the process of executing the contracts within this stage (rather than within mobilisation as in the RIBA Plan of work) because on design and build or public projects, mobilisation does not follow the tender process. | |
− | + | The tasks described below are based on the route taken by project following a construction management procurement route where a construction manager is appointed early in the project as a consultant, and then takes on a management role for the construction of the project. Tendering involves a number of trade contracts, contracted by the client but managed by the construction manager. Trade contracts may not all be tendered at the same stage, and so this process might be repeated a number of times during the project. | |
Project plans for other procurement routes area available on the home page. | Project plans for other procurement routes area available on the home page. | ||
− | NB This article is locked in order to preserve | + | NB This article is locked in order to preserve the logic and continuity of the full work plan. If you would like to propose changes or additions, click on the comment link at the bottom of the page. |
+ | <br> | ||
+ | <br> | ||
− | + | === Construction management: tender === | |
− | + | ||
− | === Construction management: tender === | + | |
---- | ---- | ||
− | '''A. Commencing the work stage.''' | + | '''A. Commencing the work stage.''' |
'''<br>''' | '''<br>''' | ||
− | The construction manager and client prepare selection criteria for trade contractors and if appropriate pre qualification questionnaires. If it is necessary and has not already been done, OJEU or other adverts are prepared. | + | #The construction manager and client prepare selection criteria for trade contractors and if appropriate pre-qualification questionnaires. If it is necessary and has not already been done, OJEU or other adverts are prepared. |
#The construction manager and client prepare a long-list of suitable trade contractors to tender for the work packages and consider the preferred form of contract and contract conditions. | #The construction manager and client prepare a long-list of suitable trade contractors to tender for the work packages and consider the preferred form of contract and contract conditions. | ||
− | #The | + | #The construction manager agrees with the client their delegated limit for issuing instructions in relation to the contract. |
− | + | #The construction manager co-ordinates a stage start-up meeting with the consultant team, and the client to agree the programme and procedures that will be adopted for tendering. The construction manager gives any instructions necessary relating to lists of approved trade contractors, any required advertising, the form of contract, contract conditions and other requirements. | |
+ | <br> | ||
---- | ---- | ||
− | '''B. Preparing the tender documentation.''' | + | '''B. Preparing the tender documentation.''' |
+ | <br> | ||
− | + | NB Throughout this stage, The lead designer co-ordinates completion of statutory approvals and other approvals and negotiations (such as party wall negotiations, negotiations with insurers etc.) | |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
+ | #The construction manager obtains from the consultant team information for the tender documentation and any other information required for the preparation of the pre-tender estimate, cash flow projection and tender pricing document. | ||
+ | #The construction manager prepares the pre-tender estimate, cash flow projection and tender pricing document. | ||
+ | #The CDM co-ordinator co-ordinates the preparation of pre-construction Information. | ||
+ | #If it has not already been done, the client prepares or arranges for the consultant team or construction manager to prepare a site waste management plan. | ||
+ | #The construction manager co-ordinates a review of the tender documents and issues instructions to make amendments if necessary. | ||
+ | #The construction manager instigates a change control procedure for the tender documents. | ||
+ | #The construction manager arranges printing of the tender documents. | ||
+ | #The client takes advise from the construction manager and decides whether to appoint, or arrange for the appointment of site inspectors (see work stage: Construction management: appointment). | ||
+ | <br> | ||
---- | ---- | ||
− | '''C. Identifying potential tenderers.''' | + | '''C. Identifying potential tenderers.''' |
'''<br>''' | '''<br>''' | ||
− | The construction manager issues pre-qualification questionnaires to the long-list of potential tenderers. | + | #The construction manager issues pre-qualification questionnaires to the long-list of potential tenderers. |
− | #The construction manager receives completed pre-qualification questionnaires from the long-list of potential tenderers. | + | #The construction manager receives completed pre-qualification questionnaires from the long-list of potential tenderers. |
− | #The construction manager carries out financial checks on potential tenderers (ideally the contract should not be more than 20% of the annual turnover of the potential tenderers). | + | #The construction manager carries out financial checks on potential tenderers (ideally the contract should not be more than 20% of the annual turnover of the potential tenderers). |
− | #Where appropriate the CDM co-ordinator advises on potential tenderers competence. | + | #Where appropriate the CDM co-ordinator advises on potential tenderers competence. |
− | #The construction manager co-ordinates | + | #The construction manager co-ordinates advice on prospective tenderers and prepares a short list of tenderers to present for client comment or approval. |
− | #The client accepts or alters the initial short list of tenderers and where appropriate the construction manager to arranges pre-tender interviews with the initial short list of tenderers. | + | #The client accepts or alters the initial short list of tenderers and where appropriate the construction manager to arranges pre-tender interviews with the initial short list of tenderers. |
− | #If necessary, following comments received during the pre-tender interviews, the construction manager instructs amendments to the tender documentation. | + | #If necessary, following comments received during the pre-tender interviews, the construction manager instructs amendments to the tender documentation. |
#Following the pre-tender interviews, the construction manager co-ordinates any amendments to the initial short list of tenderers and agrees the final short list of tenderers with the client. | #Following the pre-tender interviews, the construction manager co-ordinates any amendments to the initial short list of tenderers and agrees the final short list of tenderers with the client. | ||
− | + | <br> | |
---- | ---- | ||
− | '''D. Identifying the preferred tenderer(s).''' | + | '''D. Identifying the preferred tenderer(s).''' |
'''<br>''' | '''<br>''' | ||
− | The construction manager collates tender documents for each of the trade contracts and arranges dispatch and return to and from the tenderers. | + | #The construction manager collates tender documents for each of the trade contracts and arranges dispatch and return to and from the tenderers. |
− | #The construction manager compiles queries from tenderers and co-ordinates responses which should be issues to all tenderers. | + | #The construction manager compiles queries from tenderers and co-ordinates responses which should be issues to all tenderers. |
− | #If necessary the construction manager arranges mid tender interviews or site visits for the tenderers. | + | #If necessary the construction manager arranges mid tender interviews or site visits for the tenderers. |
#If queries from the tenderers or discussions during the mid tender interviews result in significant clarification of or changes to the tender documentation, the construction manager may recommend to the client that the tender period is extended. | #If queries from the tenderers or discussions during the mid tender interviews result in significant clarification of or changes to the tender documentation, the construction manager may recommend to the client that the tender period is extended. | ||
− | #The client receives and arranges for the opening of the tenders | + | #The client receives and arranges for the opening of the tenders. |
− | #The construction | + | #The construction manager co-ordinates the assessment of the tenders (this may include further interviews). |
+ | #The the lead designer co-ordinates assessment of any contractor's proposals submitted by tenderers. | ||
+ | #The the CDM co-ordinator assesses any initial construction phase plans submitted by the tenders. | ||
#The client receives the tender appraisals from the construction manager, and instructs the construction manager to enter into negotiations with the preferred tenderers. NB If the lead consultant disagrees with the construction managers appraisal, them may submit their own tender appraisal. | #The client receives the tender appraisals from the construction manager, and instructs the construction manager to enter into negotiations with the preferred tenderers. NB If the lead consultant disagrees with the construction managers appraisal, them may submit their own tender appraisal. | ||
− | + | <br> | |
---- | ---- | ||
− | '''E. Entering into negotiations with the preferred tenderer(s).''' | + | '''E. Entering into negotiations with the preferred tenderer(s).''' |
'''<br>''' | '''<br>''' | ||
− | The construction manager co-ordinates negotiations with the preferred tenderer(s). | + | #The construction manager co-ordinates negotiations with the preferred tenderer(s). |
− | #The construction manager co-ordinates the preparation of | + | #The construction manager co-ordinates the preparation of a tender report. |
− | #The client considers the tender report; and instructs the construction manager if any changes are required to the tender documents. | + | #The client considers the tender report; and instructs the construction manager if any changes are required to the tender documents. |
#If instructed the construction manager co-ordinates adjustments to tender documents and requests a revised tender from the preferred tenderer(s). | #If instructed the construction manager co-ordinates adjustments to tender documents and requests a revised tender from the preferred tenderer(s). | ||
− | + | <br> | |
---- | ---- | ||
− | '''F. Deciding to appoint the preferred tenderer. <br>''' | + | '''F. Deciding to appoint the preferred tenderer(s). <br>''' |
+ | Before a final investment decision is made to appoint the preferred tenderer, the client must ensure adequate funding is in place. | ||
+ | |||
+ | <br> | ||
---- | ---- | ||
− | '''G. Appointing the trade contractor | + | '''G. Appointing the trade contractor. <br>''' |
+ | |||
− | The construction manager collates the contract documents and arranges for the execution (engrossment) of two copes, one for the client and one for the trade contractor. This can take place at a specially convened signing meeting. Alternatively, the client might retain one executed contract, with certified copies being issued to the trade contractor, this can avoid potential errors in preparing two contracts for execution. This can take place at a specially convened signing meeting. The trade contractor may be required to provide; a performance bond, warranties and evidence of insurance cover. | + | |
− | #The construction manager arranges for copies of the contract documentation (or relevant parts) to be issued to the consultant team. | + | #The construction manager collates the contract documents and arranges for the execution (engrossment) of two copes, one for the client and one for the trade contractor. This can take place at a specially convened signing meeting. Alternatively, the client might retain one executed contract, with certified copies being issued to the trade contractor, this can avoid potential errors in preparing two contracts for execution. This can take place at a specially convened signing meeting. The trade contractor may be required to provide; a performance bond, warranties and evidence of insurance cover. |
+ | #The construction manager arranges for copies of the contract documentation (or relevant parts) to be issued to the consultant team. | ||
#The construction manager informs other tenderers that they have been unsuccessful. | #The construction manager informs other tenderers that they have been unsuccessful. | ||
+ | NB. Trade contracts may not all be tendered at the same stage, and so this process might be repeated a number of times during the project. <br> | ||
− | |||
+ | ---- | ||
+ | <br> | ||
− | Next work stage: | + | Next work stage: Construction management: mobilisation.<br>Previous work stage: Construction management: production information. <br>Return to: Construction management: outline work plan.<br> |
[[Category:Construction_manager]] | [[Category:Construction_manager]] |
Revision as of 09:54, 22 November 2011
The tender stage (equivalent to RIBA stage G: tender documentation and H: tender action) is the process of selecting and appointing the contractor for the main contract. We describe this stage as 'tender' rather than 'tender documentation' and 'tender action' (RIBA plan of work) to avoid the proliferation of work stages. We include the process of executing the contracts within this stage (rather than within mobilisation as in the RIBA Plan of work) because on design and build or public projects, mobilisation does not follow the tender process.
The tasks described below are based on the route taken by project following a construction management procurement route where a construction manager is appointed early in the project as a consultant, and then takes on a management role for the construction of the project. Tendering involves a number of trade contracts, contracted by the client but managed by the construction manager. Trade contracts may not all be tendered at the same stage, and so this process might be repeated a number of times during the project.
Project plans for other procurement routes area available on the home page.
NB This article is locked in order to preserve the logic and continuity of the full work plan. If you would like to propose changes or additions, click on the comment link at the bottom of the page.
Construction management: tender
A. Commencing the work stage.
- The construction manager and client prepare selection criteria for trade contractors and if appropriate pre-qualification questionnaires. If it is necessary and has not already been done, OJEU or other adverts are prepared.
- The construction manager and client prepare a long-list of suitable trade contractors to tender for the work packages and consider the preferred form of contract and contract conditions.
- The construction manager agrees with the client their delegated limit for issuing instructions in relation to the contract.
- The construction manager co-ordinates a stage start-up meeting with the consultant team, and the client to agree the programme and procedures that will be adopted for tendering. The construction manager gives any instructions necessary relating to lists of approved trade contractors, any required advertising, the form of contract, contract conditions and other requirements.
B. Preparing the tender documentation.
NB Throughout this stage, The lead designer co-ordinates completion of statutory approvals and other approvals and negotiations (such as party wall negotiations, negotiations with insurers etc.)
- The construction manager obtains from the consultant team information for the tender documentation and any other information required for the preparation of the pre-tender estimate, cash flow projection and tender pricing document.
- The construction manager prepares the pre-tender estimate, cash flow projection and tender pricing document.
- The CDM co-ordinator co-ordinates the preparation of pre-construction Information.
- If it has not already been done, the client prepares or arranges for the consultant team or construction manager to prepare a site waste management plan.
- The construction manager co-ordinates a review of the tender documents and issues instructions to make amendments if necessary.
- The construction manager instigates a change control procedure for the tender documents.
- The construction manager arranges printing of the tender documents.
- The client takes advise from the construction manager and decides whether to appoint, or arrange for the appointment of site inspectors (see work stage: Construction management: appointment).
C. Identifying potential tenderers.
- The construction manager issues pre-qualification questionnaires to the long-list of potential tenderers.
- The construction manager receives completed pre-qualification questionnaires from the long-list of potential tenderers.
- The construction manager carries out financial checks on potential tenderers (ideally the contract should not be more than 20% of the annual turnover of the potential tenderers).
- Where appropriate the CDM co-ordinator advises on potential tenderers competence.
- The construction manager co-ordinates advice on prospective tenderers and prepares a short list of tenderers to present for client comment or approval.
- The client accepts or alters the initial short list of tenderers and where appropriate the construction manager to arranges pre-tender interviews with the initial short list of tenderers.
- If necessary, following comments received during the pre-tender interviews, the construction manager instructs amendments to the tender documentation.
- Following the pre-tender interviews, the construction manager co-ordinates any amendments to the initial short list of tenderers and agrees the final short list of tenderers with the client.
D. Identifying the preferred tenderer(s).
- The construction manager collates tender documents for each of the trade contracts and arranges dispatch and return to and from the tenderers.
- The construction manager compiles queries from tenderers and co-ordinates responses which should be issues to all tenderers.
- If necessary the construction manager arranges mid tender interviews or site visits for the tenderers.
- If queries from the tenderers or discussions during the mid tender interviews result in significant clarification of or changes to the tender documentation, the construction manager may recommend to the client that the tender period is extended.
- The client receives and arranges for the opening of the tenders.
- The construction manager co-ordinates the assessment of the tenders (this may include further interviews).
- The the lead designer co-ordinates assessment of any contractor's proposals submitted by tenderers.
- The the CDM co-ordinator assesses any initial construction phase plans submitted by the tenders.
- The client receives the tender appraisals from the construction manager, and instructs the construction manager to enter into negotiations with the preferred tenderers. NB If the lead consultant disagrees with the construction managers appraisal, them may submit their own tender appraisal.
E. Entering into negotiations with the preferred tenderer(s).
- The construction manager co-ordinates negotiations with the preferred tenderer(s).
- The construction manager co-ordinates the preparation of a tender report.
- The client considers the tender report; and instructs the construction manager if any changes are required to the tender documents.
- If instructed the construction manager co-ordinates adjustments to tender documents and requests a revised tender from the preferred tenderer(s).
F. Deciding to appoint the preferred tenderer(s).
Before a final investment decision is made to appoint the preferred tenderer, the client must ensure adequate funding is in place.
G. Appointing the trade contractor.
- The construction manager collates the contract documents and arranges for the execution (engrossment) of two copes, one for the client and one for the trade contractor. This can take place at a specially convened signing meeting. Alternatively, the client might retain one executed contract, with certified copies being issued to the trade contractor, this can avoid potential errors in preparing two contracts for execution. This can take place at a specially convened signing meeting. The trade contractor may be required to provide; a performance bond, warranties and evidence of insurance cover.
- The construction manager arranges for copies of the contract documentation (or relevant parts) to be issued to the consultant team.
- The construction manager informs other tenderers that they have been unsuccessful.
NB. Trade contracts may not all be tendered at the same stage, and so this process might be repeated a number of times during the project.
Next work stage: Construction management: mobilisation.
Previous work stage: Construction management: production information.
Return to: Construction management: outline work plan.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.