Construction management: post occupation evaluation
Line 3: | Line 3: | ||
Ideally the client should commit to carrying out post occupancy evaluation at the beginning of the project so that appointment agreements and briefing documents can include a requirement to test whether objectives were achieved. | Ideally the client should commit to carrying out post occupancy evaluation at the beginning of the project so that appointment agreements and briefing documents can include a requirement to test whether objectives were achieved. | ||
− | We attribute activities in this stage to a 'consultant', but they may be carried out by an in-house team established by the client | + | We attribute activities in this stage to a 'consultant', but they may be carried out by an in-house team established by the client. |
The tasks described below are based on the route taken by project following a construction management procurement route where a construction manager is appointed early in the project as a consultant, and then takes on a management role for the construction of the project. Project plans for other procurement routes are available on the Designing Buildings Wiki home page. | The tasks described below are based on the route taken by project following a construction management procurement route where a construction manager is appointed early in the project as a consultant, and then takes on a management role for the construction of the project. Project plans for other procurement routes are available on the Designing Buildings Wiki home page. | ||
Line 27: | Line 27: | ||
'''B. Carrying out a post project review (to evaluate the project delivery process).''' | '''B. Carrying out a post project review (to evaluate the project delivery process).''' | ||
− | + | NB A post project review may commence during the defects liability period. Its purpose is to evaluate the project delivery process rather than to assess performance in use (which is assessed later in this stage). | |
+ | |||
+ | |||
#The consultant and client hold a start-up meeting to confirm the scope of evaluation required and agree the reporting procedures and programme for the stage. The client issues relevant information that may have been compiled during the design and construction phases to the consultant. | #The consultant and client hold a start-up meeting to confirm the scope of evaluation required and agree the reporting procedures and programme for the stage. The client issues relevant information that may have been compiled during the design and construction phases to the consultant. | ||
Line 44: | Line 46: | ||
'''C. Agreeing the procedures for assessing performance in use.''' | '''C. Agreeing the procedures for assessing performance in use.''' | ||
− | + | NB Performance in use assessments cannot begin until at least 6 to 12 months after occupation (operations may not be properly established, and the building will not have operated in all seasons) and then may be part of a continuous process. | |
+ | |||
+ | |||
#The consultant and client hold a start-up meeting to confirm the scope of the evaluation required and agree the reporting procedures and programme for the assessment. The client issues relevant information that may have been compiled during the design and construction phases to the consultant. | #The consultant and client hold a start-up meeting to confirm the scope of the evaluation required and agree the reporting procedures and programme for the assessment. The client issues relevant information that may have been compiled during the design and construction phases to the consultant. | ||
Line 104: | Line 108: | ||
<br> | <br> | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
[[Category:Construction_manager]] | [[Category:Construction_manager]] |
Revision as of 08:51, 8 December 2011
Post occupancy evaluation (equivalent to RIBA stages L2: initial occupation services and L3: post occupation evaluation services, or OGC's post implementation review) is the process of evaluating the development in use to determine how successful the delivery of the project was, how successful the completed development is, where there is potential for further improvement, and what lessons can be learned for future projects. Post occupancy evaluation can be particularly valuable to repeat developers and may be a requirement of some funding bodies. We describe the stage as post occupancy evaluation rather than 'initial occupation services' and 'post occupation evaluation services' (RIBA) to avoid the proliferation of stages. In practice, post occupancy evaluation may begin during the defects liability period.
Ideally the client should commit to carrying out post occupancy evaluation at the beginning of the project so that appointment agreements and briefing documents can include a requirement to test whether objectives were achieved.
We attribute activities in this stage to a 'consultant', but they may be carried out by an in-house team established by the client.
The tasks described below are based on the route taken by project following a construction management procurement route where a construction manager is appointed early in the project as a consultant, and then takes on a management role for the construction of the project. Project plans for other procurement routes are available on the Designing Buildings Wiki home page.
NB This article is locked in order to preserve the logic and continuity of the full work plan. If you would like to propose changes or additions, click on the 'submit comment' link at the bottom of the page.
Construction management: post occupancy evaluation.
A. Appointing consultants.
- Post occupancy evaluations may be carried out by an in house team, or by members of the consultant team or independent client advisers (we attribute them below to a consultant for simplicity of presentation). However, as post occupancy evaluation is likely to take place after the main construction contract has been completed, consultant team appointments may also be completed (unless post occupation services were a specific requirement of the original appointment agreements). If such services were not a requirement of the original appointments then new appointments may be necessary. Go to work stage: Construction management: appointment.
B. Carrying out a post project review (to evaluate the project delivery process).
NB A post project review may commence during the defects liability period. Its purpose is to evaluate the project delivery process rather than to assess performance in use (which is assessed later in this stage).
- The consultant and client hold a start-up meeting to confirm the scope of evaluation required and agree the reporting procedures and programme for the stage. The client issues relevant information that may have been compiled during the design and construction phases to the consultant.
- The consultant makes site visits to identify any issues that need to be addressed immediately.
- The consultant may establish a help-desk and rapid response team if this has not already been done by the client.
- The consultant monitors completion of the building owner's manual (operation and maintenance manual) if this has not already been completed and ensures that other project documentation has been properly completed and handed over to the client (see handover to the client). This may include preparation of 'as built' or 'as manufactured and installed' drawings.
- The consultant obtains the views of the construction manager, trade contractors, designers, suppliers and the client about how well the project was managed. This may include assessments of: the quality briefing documents; the effectiveness of communications; the performance of the entire project team; quality issues; health and safety issues; certification; variations; claims disputes; and collaborative practices.
- The consultant considers how well the delivery of the project performed against key performance indicators.
- The consultant evaluates what lessons can be learned from the approach taken.
- The consultant prepares an assessment and lessons learned report for the client.
C. Agreeing the procedures for assessing performance in use.
NB Performance in use assessments cannot begin until at least 6 to 12 months after occupation (operations may not be properly established, and the building will not have operated in all seasons) and then may be part of a continuous process.
- The consultant and client hold a start-up meeting to confirm the scope of the evaluation required and agree the reporting procedures and programme for the assessment. The client issues relevant information that may have been compiled during the design and construction phases to the consultant.
D. The consultant carries out evaluations of business objectives, which may include:
- The achievement of business case objectives.
- Whole-life costs and benefits against those forecast (including assessment of capital vs running costs).
- Whether the project continues to comply with the business strategy.
- Whether operations have improved.
- The resilience of the development and business to change.
- Business and user satisfaction (including staff and user retention and motivation).
E. The consultant carries out evaluations of the design, which may include:
- The effectiveness of the space planning.
- Aesthetic quality.
- The standards of lighting, acoustic environment, ventilation, temperature and humidity.
- Air-pollution and air quality.
- User comfort.
- Maintenance and occupancy costs.
- Defects.
- The balance between capital and running costs.
- Environmental and energy consumption in use. NB Regular evaluation of energy consumption is mandatory for certain types of buildings under the Energy Performance of Buildings (Certificates and Inspections) (England and Wales) Regulations). See the article on energy certificates for more information.
F. The consultant prepares a report that:
- Compares their findings to the original targets set out in business case (the original targets may need to be updated to reflect changes to the project brief during the design process, inflation etc).
- Compares findings to other projects and industry standards.
- Compares the outcome of the project with the position had the project not taken place.
- Identifies issues and recommends remedies.
- Makes recommendations for improvements in performance on future projects.
NB other services that could be provided by consultants during this period might include: providing advice on letting, rating, maintenance, energy consumption, insurance, tenants queries, facilities management, the production of energy performance certificates, BREEAM assessments, the preparation of tender documents for maintenance and operation contracts and so on.
Return to: Construction management: outline work plan.
Previous stage: Construction management: occupation and defects liability period.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.