CDM 2015 contractor duties
Line 12: | Line 12: | ||
The duties of contractors have changed slightly from the 2007 regulations. | The duties of contractors have changed slightly from the 2007 regulations. | ||
− | Contractors are defined in the 2015 CDM Regulations as ‘…those who do the actual construction work and can be either an individual or a company’ that is, ‘…anyone who directly employs or engages construction workers or manages construction is a contractor. An individual, a sole trader, a self-employed worker, or a business that carries out, manages or controls construction work as part of their business can be a contractor. This also includes companies that use their own workforce to do construction work on their own premises. The duties on contractors apply whether the workers under their control are employees, self-employed or agency workers.’ | + | Contractors are defined in the guidance to the 2015 CDM Regulations as ‘…those who do the actual construction work and can be either an individual or a company’ that is, ‘…anyone who directly employs or engages construction workers or manages construction is a contractor. An individual, a sole trader, a self-employed worker, or a business that carries out, manages or controls construction work as part of their business can be a contractor. This also includes companies that use their own workforce to do construction work on their own premises. The duties on contractors apply whether the workers under their control are employees, self-employed or agency workers.’ |
On projects where there is more than one contractor, the client must appoint a principal contractor to plan, manage, monitor and coordinate the construction phase of the project. | On projects where there is more than one contractor, the client must appoint a principal contractor to plan, manage, monitor and coordinate the construction phase of the project. | ||
Line 22: | Line 22: | ||
*Complying with the construction phase plan. | *Complying with the construction phase plan. | ||
*Ensuring subcontractors and designers they appoint have the skills, knowledge and experience and, where relevant, organisational capability to carry out the work for which they are being appointed. | *Ensuring subcontractors and designers they appoint have the skills, knowledge and experience and, where relevant, organisational capability to carry out the work for which they are being appointed. | ||
− | *Making enquiries to ensure | + | *Making enquiries to ensure the individuals they appoint have the necessary skills, knowledge, training and experience to carry out works in a way that secures health and safety for anyone working on the site; or that they are in the process of obtaining them. |
*Establishing whether training is necessary for any worker. | *Establishing whether training is necessary for any worker. | ||
*Ensuring that appropriate supervision is provided. | *Ensuring that appropriate supervision is provided. | ||
− | *Providing employees and workers under their control with the information and instructions they need to carry out their work without risk to health and safety. This must include a site induction, emergency procedures and information about hazards. | + | *Providing employees and workers under their control with the information and instructions they need to carry out their work without risk to health and safety. This must include a site induction, information about emergency procedures and information about relevant hazards. |
*Not beginning work on site unless reasonable steps have been taken to prevent unauthorised access to the site. | *Not beginning work on site unless reasonable steps have been taken to prevent unauthorised access to the site. | ||
*Providing welfare facilities. On projects involving more than one contractor, this will involve consultation with the principal contractor who has a similar duty. | *Providing welfare facilities. On projects involving more than one contractor, this will involve consultation with the principal contractor who has a similar duty. | ||
*Not carrying out any construction work unless they are satisfied that the client is aware of their duties under the regulations. | *Not carrying out any construction work unless they are satisfied that the client is aware of their duties under the regulations. | ||
− | If the client fails to appoint a principal contractor, the client must fulfil the duties of the principal contractor. However, if a domestic client fails to make an appointment, the contractor in control of the construction phase of the project is the principal contractor. This gives | + | If the client fails to appoint a principal contractor, the client must fulfil the duties of the principal contractor. However, if a domestic client fails to make an appointment, the contractor in control of the construction phase of the project is the principal contractor. This gives them a number of additional duties, including preparing a construction phase plan. See CDM 2015 principal contractor for more information. |
A domestic client is someone who has construction work done on their own home, or the home of a family member, which is not done in connection with a business. | A domestic client is someone who has construction work done on their own home, or the home of a family member, which is not done in connection with a business. | ||
− | Where a client is a domestic client, the principal contractor must carry out the duties of the client under the regulations, however, where there is only one contractor, this means the contractor must carry out | + | Where a client is a domestic client, the principal contractor must carry out the duties of the client under the regulations, however, where there is only one contractor, this means the contractor must carry out those duties (unless there is a written agreement that the principal designer will fulfil them). See Client duties under CDM 2015. |
Where contractors are involved in design work, including for temporary works, they also have duties as designers. | Where contractors are involved in design work, including for temporary works, they also have duties as designers. |
Revision as of 10:15, 19 February 2015
The Construction (Design and Management) Regulations (the ‘CDM Regulations’) are intended to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced. They were introduced in 1994 and revised in 2007. A further revision will come into force on 6 April 2015.
The 2015 CDM regulations include duties for:
- Clients. See CDM 2015 client duties.
- Designers.
- Principal designers. See CDM 2015 principal designer duties.
- Principal contractors. See CDM 2015 principal contractor duties.
- Contractors.
- Workers.
The duties of contractors have changed slightly from the 2007 regulations.
Contractors are defined in the guidance to the 2015 CDM Regulations as ‘…those who do the actual construction work and can be either an individual or a company’ that is, ‘…anyone who directly employs or engages construction workers or manages construction is a contractor. An individual, a sole trader, a self-employed worker, or a business that carries out, manages or controls construction work as part of their business can be a contractor. This also includes companies that use their own workforce to do construction work on their own premises. The duties on contractors apply whether the workers under their control are employees, self-employed or agency workers.’
On projects where there is more than one contractor, the client must appoint a principal contractor to plan, manage, monitor and coordinate the construction phase of the project.
The duties of a contractor under the regulations include:
- Planning, managing and monitoring construction work under their control so that it is carried out without risks to health and safety, taking into account the risks to all those who may be affected, such as members of the public and those carrying out the construction work.
- Cooperating with other dutyholders.
- For projects involving more than one contractor, complying with directions given to them by the principal designer or principal contractor.
- Complying with the construction phase plan.
- Ensuring subcontractors and designers they appoint have the skills, knowledge and experience and, where relevant, organisational capability to carry out the work for which they are being appointed.
- Making enquiries to ensure the individuals they appoint have the necessary skills, knowledge, training and experience to carry out works in a way that secures health and safety for anyone working on the site; or that they are in the process of obtaining them.
- Establishing whether training is necessary for any worker.
- Ensuring that appropriate supervision is provided.
- Providing employees and workers under their control with the information and instructions they need to carry out their work without risk to health and safety. This must include a site induction, information about emergency procedures and information about relevant hazards.
- Not beginning work on site unless reasonable steps have been taken to prevent unauthorised access to the site.
- Providing welfare facilities. On projects involving more than one contractor, this will involve consultation with the principal contractor who has a similar duty.
- Not carrying out any construction work unless they are satisfied that the client is aware of their duties under the regulations.
If the client fails to appoint a principal contractor, the client must fulfil the duties of the principal contractor. However, if a domestic client fails to make an appointment, the contractor in control of the construction phase of the project is the principal contractor. This gives them a number of additional duties, including preparing a construction phase plan. See CDM 2015 principal contractor for more information.
A domestic client is someone who has construction work done on their own home, or the home of a family member, which is not done in connection with a business.
Where a client is a domestic client, the principal contractor must carry out the duties of the client under the regulations, however, where there is only one contractor, this means the contractor must carry out those duties (unless there is a written agreement that the principal designer will fulfil them). See Client duties under CDM 2015.
Where contractors are involved in design work, including for temporary works, they also have duties as designers.
Specific requirements are set out in relation to:
- Safe places of construction work.
- Good order and site security.
- Stability of structures.
- Demolition or dismantling.
- Explosives.
- Excavations.
- Cofferdams and caissons.
- Reports of inspections.
- Energy distribution installations.
- Prevention of drowning.
- Traffic routes.
- Vehicles.
- Prevention of risk from fire, flooding or asphyxiation.
- Emergency procedures.
- Emergency routes and exits.
- Fire detection and fire-fighting.
- Fresh air.
- Temperature and weather protection.
- Enforcement in respect of fire.
Find out more
Related articles on Designing Buildings Wiki
- CDM.
- CDM 2015.
- CDM 2015 draft guidance.
- CDM 2015 client duties.
- CDM 2015 principal contractor duties.
- CDM 2015 principal designer duties.
- CDM for self-builders and domestic clients.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.