Preliminaries in construction
Line 1: | Line 1: | ||
+ | |||
Preliminaries are part of the tender documents prepared by (or on behalf of) the client. They provide a description of the project that allows the contractor to assess costs which, whilst they do not form a part of any package of works, are required by the method and circumstances of the works. Preliminaries should not be confused with 'preambles' which set out things such as tendering procedures, that will not affect the contractor's price. | Preliminaries are part of the tender documents prepared by (or on behalf of) the client. They provide a description of the project that allows the contractor to assess costs which, whilst they do not form a part of any package of works, are required by the method and circumstances of the works. Preliminaries should not be confused with 'preambles' which set out things such as tendering procedures, that will not affect the contractor's price. | ||
Preliminaries may contain: | Preliminaries may contain: | ||
− | |||
*A general summary. | *A general summary. | ||
*Method statements. | *Method statements. | ||
Line 29: | Line 29: | ||
*Contractor's site preliminaries, such as; staff, welfare provisions, site offices, plant, site waste clearance, water, electricity, site offices, furniture, ICT and consumables, rates, protection of work, protective clothing, site transport, setting out, building control fees, etc. | *Contractor's site preliminaries, such as; staff, welfare provisions, site offices, plant, site waste clearance, water, electricity, site offices, furniture, ICT and consumables, rates, protection of work, protective clothing, site transport, setting out, building control fees, etc. | ||
− | NB The [http://www.cpic.org.uk/en/test_section/caws.cfm Common Arrangement of Work Sections for Building Works] (CAWS) sets out detailed categorises for preliminaries. | + | NB The [http://www.cpic.org.uk/en/test_section/caws.cfm Common Arrangement of Work Sections for Building Works] (CAWS) sets out detailed categorises for preliminaries. Although this system is currently undergoing considerable change, with [http://www.designingbuildings.co.uk/wiki/CAWS CAWS] being incorporated into Uniclass, Uniclass being replaced with Uniclass2 and SMM7 being superceded by the New Rules of Measurement (NRM). See CAWS for more information. |
− | = | + | = Find out more = |
+ | === Related articles on Designing Buildings Wiki === | ||
*Attendance. | *Attendance. | ||
*Provisional sums. | *Provisional sums. | ||
+ | *CAWS | ||
*Construction progress meetings. | *Construction progress meetings. | ||
*Construction progress reports. | *Construction progress reports. | ||
+ | |||
+ | === External references === | ||
*[http://www.thenbs.com/products/nbsPreliminaries.asp nbs definition of preliminaries]. | *[http://www.thenbs.com/products/nbsPreliminaries.asp nbs definition of preliminaries]. | ||
*CPIC: [http://www.cpic.org.uk/en/test_section/caws.cfm Common arrangement of work sections]. | *CPIC: [http://www.cpic.org.uk/en/test_section/caws.cfm Common arrangement of work sections]. | ||
− | *PACE [[F | + | *PACE [[F%20http%3A%2F%2Fwebarchive.nationalarchives.gov.uk%2F20100503135839%2Fhttp%3A%2F%2Fwww.ogc.gov.uk%2Fdocuments%2FPACE%20-%20GACC.pdf|Guidance on the Appointment of Consultants and Contractors]] P404. |
− | + | ||
[[Category:Contracts_/_payment]] | [[Category:Contracts_/_payment]] | ||
[[Category:Procurement]] | [[Category:Procurement]] |
Revision as of 12:18, 10 December 2012
Preliminaries are part of the tender documents prepared by (or on behalf of) the client. They provide a description of the project that allows the contractor to assess costs which, whilst they do not form a part of any package of works, are required by the method and circumstances of the works. Preliminaries should not be confused with 'preambles' which set out things such as tendering procedures, that will not affect the contractor's price.
Preliminaries may contain:
- A general summary.
- Method statements.
- Pre-construction information.
- Details of any alternative options to be put forward by tenderers.
- A description of any planning or other conditions that may affect the work to be carried out by the contractor.
- A description of any outstanding statutory approvals that may fall to the contractor to satisfy.
- Party wall requirements or other agreements with neighbours (such as rights to light).
- Any emergency services obligations.
- A description of the reporting information that the contractor will be required to submit (often on a monthly basis) describing construction progress (including a detailed critical path programme, key performance indicators and earned value analysis). See construction progress reports for more information.
- A description of the commissioning strategy, separating 'setting to work and balancing tasks' from the independent verification by the consultant team.
- Relevant reports (such as soil reports).
- Perhaps an information release schedule.
- Quality management procedures.
- Labour relations.
- A declaration of non-collusion.
- Schedules of mock-ups, testing and samples required from the contractor.
- The method of sub-contracting.
- Requirements for insurance, performance bonds, warranties and product guarantees (for the contractor and sub-contractors).
- Requirements for the operating and maintenance manual (the client's facilities management team may wish to comment on this).
- Requirement for progress photos to be taken on site during construction and off-site during fabrication.
- Dates for partial possession.
- Collaborative practices.
- Building information modelling (BIM) requirement and protocols (including requirement for BIM in sub-contracts).
- Site waste management plan.
- Contractor's site preliminaries, such as; staff, welfare provisions, site offices, plant, site waste clearance, water, electricity, site offices, furniture, ICT and consumables, rates, protection of work, protective clothing, site transport, setting out, building control fees, etc.
NB The Common Arrangement of Work Sections for Building Works (CAWS) sets out detailed categorises for preliminaries. Although this system is currently undergoing considerable change, with CAWS being incorporated into Uniclass, Uniclass being replaced with Uniclass2 and SMM7 being superceded by the New Rules of Measurement (NRM). See CAWS for more information.
Find out more
Related articles on Designing Buildings Wiki
- Attendance.
- Provisional sums.
- CAWS
- Construction progress meetings.
- Construction progress reports.
External references
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.