Liquidated v unliquidated damages
(Created page with "Contracts generally include a provision for the contractor to pay liquidated damages (or liquidated and ascertained damages, sometimes referred to as LAD's) to the client in the ...") |
|||
Line 1: | Line 1: | ||
Contracts generally include a provision for the contractor to pay liquidated damages (or liquidated and ascertained damages, sometimes referred to as LAD's) to the client in the event that the contract is breached. | Contracts generally include a provision for the contractor to pay liquidated damages (or liquidated and ascertained damages, sometimes referred to as LAD's) to the client in the event that the contract is breached. | ||
+ | |||
+ | Liquidated damages are a pre-agreed amount of money that is contained in a clause provision to a contract, that fixes the sum payable as damages if one of the parties breaches the contract. It is usually agreed in the contract what will constitute a breach that requires a payment of liquidated damages. | ||
In building contracts, liquidated damages usually relate to the contractor failing to achieve practical completion (i.e. completing the works so they can handover the site to the client) by the completion date set out in the contract. | In building contracts, liquidated damages usually relate to the contractor failing to achieve practical completion (i.e. completing the works so they can handover the site to the client) by the completion date set out in the contract. | ||
− | |||
− | |||
Unliquidated damages are damages that are payable for a breach, the exact amount of which has not been pre-agreed. The sum to be paid as compensation – which is said to be ‘at large’ - is determined after a breach occurs by a court (either a judge or jury). In standard form construction contracts, parties will sometimes insert ‘NIL’ or ‘n/a’ for the rate for liquidated damages. The proper construction of the contract as a whole will determine the effect of ‘NIL’. | Unliquidated damages are damages that are payable for a breach, the exact amount of which has not been pre-agreed. The sum to be paid as compensation – which is said to be ‘at large’ - is determined after a breach occurs by a court (either a judge or jury). In standard form construction contracts, parties will sometimes insert ‘NIL’ or ‘n/a’ for the rate for liquidated damages. The proper construction of the contract as a whole will determine the effect of ‘NIL’. | ||
− | + | One of the key advantages of a liquidated damages clause is that there is no need to prove the actual loss since the clause provides a pre-estimation of the damages to be paid. In addition to helping recover damages, this helps to provide certainty to the parties, simplifies the dispute resolution procedure, and may induce performance of the contract. | |
The advantage of unliquidated damages is that it allows for recovery of losses even though the damages were impossible to estimate with any certainty before the breach. This can also extend to damages that depend on a certain event occurring or not occurring. | The advantage of unliquidated damages is that it allows for recovery of losses even though the damages were impossible to estimate with any certainty before the breach. This can also extend to damages that depend on a certain event occurring or not occurring. | ||
If parties wish to exclude liability for unliquidated damages, they must state it clearly in the contract to avoid ambiguity. Liquidated damages provided for under the contract should be stated as being the sole remedy available for breaches of the contract. | If parties wish to exclude liability for unliquidated damages, they must state it clearly in the contract to avoid ambiguity. Liquidated damages provided for under the contract should be stated as being the sole remedy available for breaches of the contract. | ||
− | |||
− | |||
In the case of ‘Temloc Ltd. v Errill Properties Ltd.’ [1987], the court decided that 20 unliquidated damages claims that had been excluded by the use of ‘£ Nil’ could not be awarded since the parties had agreed that damages for late completion were to be specifically liquidated, rather than unliquidated, damages. | In the case of ‘Temloc Ltd. v Errill Properties Ltd.’ [1987], the court decided that 20 unliquidated damages claims that had been excluded by the use of ‘£ Nil’ could not be awarded since the parties had agreed that damages for late completion were to be specifically liquidated, rather than unliquidated, damages. |
Revision as of 17:23, 23 November 2017
Contracts generally include a provision for the contractor to pay liquidated damages (or liquidated and ascertained damages, sometimes referred to as LAD's) to the client in the event that the contract is breached.
Liquidated damages are a pre-agreed amount of money that is contained in a clause provision to a contract, that fixes the sum payable as damages if one of the parties breaches the contract. It is usually agreed in the contract what will constitute a breach that requires a payment of liquidated damages.
In building contracts, liquidated damages usually relate to the contractor failing to achieve practical completion (i.e. completing the works so they can handover the site to the client) by the completion date set out in the contract.
Unliquidated damages are damages that are payable for a breach, the exact amount of which has not been pre-agreed. The sum to be paid as compensation – which is said to be ‘at large’ - is determined after a breach occurs by a court (either a judge or jury). In standard form construction contracts, parties will sometimes insert ‘NIL’ or ‘n/a’ for the rate for liquidated damages. The proper construction of the contract as a whole will determine the effect of ‘NIL’.
One of the key advantages of a liquidated damages clause is that there is no need to prove the actual loss since the clause provides a pre-estimation of the damages to be paid. In addition to helping recover damages, this helps to provide certainty to the parties, simplifies the dispute resolution procedure, and may induce performance of the contract.
The advantage of unliquidated damages is that it allows for recovery of losses even though the damages were impossible to estimate with any certainty before the breach. This can also extend to damages that depend on a certain event occurring or not occurring.
If parties wish to exclude liability for unliquidated damages, they must state it clearly in the contract to avoid ambiguity. Liquidated damages provided for under the contract should be stated as being the sole remedy available for breaches of the contract.
In the case of ‘Temloc Ltd. v Errill Properties Ltd.’ [1987], the court decided that 20 unliquidated damages claims that had been excluded by the use of ‘£ Nil’ could not be awarded since the parties had agreed that damages for late completion were to be specifically liquidated, rather than unliquidated, damages.
Find out more
Related articles on Designing Buildings Wiki
- Breach of contract.
- Collateral warranty.
- Completion date.
- Damages in construction contracts.
- Liquidated damages.
- Measure of damages.
- Practical completion.
- The distinction between liquidated damages clauses and penalty clauses.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.