Site selection and acquisition for construction
Site selection and acquisition is crucial when the client does not own the site to be developed. It should be undertaken as early as possible, ideally, in parallel with feasibility studies. This work may be carried out by a specialist consultant.
Key to the process is ensuring that the requirements for the site are properly defined, that the selected site meets these requirements and that it is acquired within the constraints of the project programme and with minimal risk to the client.
To achieve these objectives the following tasks need to be carried out:
- Preparing a statement of objectives/requirements for the site and facility/buildings and agreeing this with the client.
- Preparing a specification for site selection, establishing the criteria for evaluating sites based on the objectives/requirements and agreeing weightings with the client.
- Establishing the outline funding arrangements.
- Determining responsibilities within the project team (client/project manager/commercial property agent).
- Appointing/briefing members of the team and developing a schedule for site selection and acquisition; monitoring and controlling progress against the schedule.
- Actioning site searches and collecting data on sites, including local planning requirements, for evaluation against the criteria. See technical due diligence and site appraisals for more information.
- Evaluating sites against the criteria and producing a short list of three or four.
- Establishing initial options and developing costs.
- Discussing short-listed sites with relevant planning authorities.
- Obtaining advice on the approximate open-market value of short-listed sites.
- Selecting the preferred site from the short list.
- Appointing agents for price negotiation and separate agents for independent valuation.
- Appointing lawyers as appropriate.
- Determining specific financial arrangements.
- Exchanging contracts for site acquisition once terms are agreed, conditional upon relevant matters, such as ground investigation, planning consent and so on.
The text in this article is based on an extract from PROJECT MANAGEMENT, by Eric Stokes and Saleem Akram. The original manual was published in 2008. It was developed within the scope of the LdV program, project number: 2009-1-PL1-LEO05-05016 entitled “Common Learning Outcomes for European Managers in Construction”. It is reproduced here in a slightly modified form with the kind permission of the Chartered Institute of Building.
--CIOB
[edit] Related articles on Designing Buildings Wiki
- Applying for new postal addresses.
- Building People.
- Condition survey.
- Contaminated land.
- Developer.
- Gross development value.
- Ground conditions.
- Land acquisition.
- Overage.
- Overbuild.
- Restrictive covenants.
- Right of way.
- Site appraisal.
- Site information.
- Site surveys.
- Soil survey.
- Technical due diligence.
- Vacant possession.
- What is a housing start?
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.