Abatement is a defence against a claim for payment where it is argued that the amount claimed is incorrect because of defects in the work. If the defect is proved, then the valuation of the amount due may be reduced by the reduction in value of the works resulting from the defect. Abatement only applies to payment for labour and materials, not to professional services or to losses resulting from delay or disruption. Abatement exists as a common law right.
Abatement is often confused with set off. Set off (or contra charging) requires that a breach of contract can be demonstrated. It can permit the withholding or extinguishing of an agreed payment. Set off can be used to recover the costs of rectifying defects and any delay. Whilst set off is often accompanied by a counterclaim it is to be distinguished in that set off cannot, unlike a counterclaim, give rise to a positive balance of claim. Set off rights can either be contractual, equitable or in the case of insolvency, statutory.
Before the 2011 amendments to the Housing Grants Construction and Regeneration Act, set off and counterclaim were only permitted if a withholding notice was issued, whilst abatement did not require a withholding notice as the value of the works had been reduced and there was only an obligation to pay the amount properly due.
Since 2011 however, set off, counterclaim and abatement all require that a pay less notice is issued.
[edit] Related articles on Designing Buildings
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.
Comments
Abatement is a defence against a claim for payment where it is argued that the amount claimed is incorrect because of defects in the work. If the defect is proved, then the valuation of the amount due may be reduced by the reduction in value of the works resulting from the defect.