Abortive work in building design and construction
Abortive work (or abortive costs or abortive fees) refers to work that has been started or carried out, but is not needed, or is no longer needed, and will not form part of the final development. The work will be wasted.
Abortive work can occur at any stage of a project, relating to the tender process, the work of consultants or construction.
Abortive work can arise because of:
- Cancellation of a project or an element of a project.
- Failed or abortive tendering.
- A change of circumstances (for example a change in legislative requirements).
- Clarification of circumstances (for example the opening up of existing works, or below ground works).
- Refusal of planning permission or other approvals.
- Changes in requirements, such as budget, location, size and technical requirements.
- The work carried out was unauthorised.
- The work was not properly authorised.
- Mistakes or misunderstandings.
- Clashes resulting from poor co-ordination.
- Design changes during manufacture or construction.
- Changes required once the completed works have been seen.
- Procurement of redundant goods, materials, plant or personnel.
The occurrence of abortive work can be reduced by:
- Undertaking thorough site investigations and condition surveys.
- Ensuring that the project brief is comprehensive and is supported by all stakeholders (including end users).
- Ensuring that legislative requirements are properly integrated into the project.
- Ensuring that risks are properly identified.
- Introducing change-control procedures at key stages, with progressive gateways at which the project is defined, agreed, a decision taken to proceed to the next stage and some aspects frozen.
- Applying for permissions as early as is practicable.
- Ensuring designs are properly co-ordinated before tender.
- Limiting the number of tenderers and the extent of the tender process (particularly for procurement routes such as the private finance initiative, or prime contracting for which tender costs can be very high) .
- Only tendering for work where the chance of success is high.
- Adopting quality assurance systems.
- Adopting assistive technologies such as building information modelling (BIM) to improve co-ordination.
- Frequent site inspections.
- Suspending the works while potential changes are assessed in order to minimise potential abortive works.
Where abortive work is carried out, the cost of those works will be allocated depending on the wording of the contract.
Very broadly, the costs may be borne by the client if the conditions set out in the contract have been met (sometimes referred to as abortive terms), if the client has accepted the risk for unknown items (such as ground conditions) or if there has been a breach of contract by the client.
Where a change has been instructed by the client in accordance with the contract that might result in abortive work, this may give rise to additions or deductions from the contract sum and may also (but not necessarily) require adjustment of the completion date.
Where the consultant or contractor has carried out unauthorised or non-compliant work, or they have accepted the risk for unknown items, they may bear the cost of abortive work.
[edit] Related articles on Designing Buildings Wiki
- Change control procedure
- Cost control.
- Remedial work.
- Scope creep.
- Variation.
- Value engineering.
- Value management.
[edit] External references
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.
Comments