Assignment of choses in action
Choses in action are ‘…all personal rights of property which can only be claimed or enforced by action and not by taking physical possession.’ (ref Torkington v Magee). The term includes the benefits arising under a contract and, subject to certain qualifications, rights of action arising by reason of a breach of contract.
A chose in action can be a legal chose, for example an interim payment due under a building contract, or an equitable chose such as a legacy under a will or an interest in a partnership.
Choses in action can be assigned or transferred unilaterally, for example A the employer enters into a construction contract with B the contractor, requiring B to construct a building to a quality set out in the specification. A can, without the consent of, or indeed knowledge of B, transfer the benefit of that contract to a third party C. A is known as the assignor, B the debtor and C the assignee. Only the benefits of a contract can be assigned, not the burdens (see Nokes v Doncaster Amalgamated Collieries). The burden must be novated.
It is important to understand that the right to assign a chose in action is not derived from contract. It is a statutory right, alternatively a right arising from the rules of equity. Express conditions are commonly found in collateral warranties purporting to grant rights of assignment; these conditions are unnecessary and may actually have the effect of restricting the rights to assign.
[edit] Related articles on Designing Buildings
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.