CDM 2007 principal contractor
For information about the role of the principal contractor under the 2015 CDM regulations see CDM 2015 principal contractor.
The text below relates to the superseded 2007 CDM regulations and is provided as a historical reference.
The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure health and safety issues are properly considered during a project’s development so the risk of harm to those who have to build, use and maintain structures is reduced.
They were introduced in 1994 and came into force on 31 March 1995. They were substantially revised in 2007.
The regulations impose duties on:
- The client. (See CDM client for more information)
- Designers. (See CDM designers for more information)
- The CDM co-ordinator.
- The principal contractor.
- Contractors. (See CDM contractors for more information)
- Workers. (See CDM workers for more information)
The regulations require that a principal contractor is appointed for all notifiable projects as soon as practicable and at the latest before construction works begin. Notifiable projects are those which last more than 30 days or involve 500 person days of construction work.
The CDM co-ordinator must inform the Health and Safety Executive of the appointment of the principal contractor.
The main contractor will usually be the principal contractor. The principal contractor's role is to plan, manage and co-ordinate health and safety during construction.
The duties of the principal contractor include:
- Preparing a construction phase plan (at least an initial construction phase plan for the early stages of the works must be prepared before construction work can begin).
- Providing contractors with information allowing them to work safely.
- Ensuring co-operation and co-ordination between parties involved in the works.
- Ensuring that other contractors identify, assess and manage risks.
- Ensuring that welfare facilities are in place.
- Ensuring that the workforce is inducted, informed, trained and consulted.
- Taking steps to prevent unauthorised access to the site.
- Displaying the required F10 notice on the site.
- Liaising with the CDM co-ordinator regarding any design work.
It is important that the principal contractor is appointed as early as possible in order to allow them sufficient time to prepare the construction phase plan. The CDM planning period is a period allowed by the client to the principal contractor referred to in regulation 15(b) of the CDM regulations for planning and preparing for construction work.
[edit] Related articles on Designing Buildings Wiki
- CDM.
- CDM 2015 principal contractor.
- CDM client.
- CDM contractors.
- CDM co-ordinators.
- CDM designers.
- CDM planning period.
- CDM workers.
- Client.
- Construction phase plan.
- Contractor.
- Health and safety.
- Health and safety file.
- Notify HSE.
- Pre-construction information.
- Site induction.
- Site waste management plan.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.