Design chill
Building design is generally an iterative process in which the design becomes more detailed and more 'fixed' as the project progresses.
At certain stages in the design process, packages of information are prepared for the client to approve, and once this approval has been given, the design is ‘frozen’ and change control procedures are introduced to ensure that no more changes are made without the permission of the client.
However, there can be an intermediate stage before design freeze, known as ‘design chill’ or ‘part freeze’.
The Construction Special Interest Group, Competency Working Group (ConSIG CWG) of the Chartered Quality Institute (CQI) suggest that:
At design chill, all aspects of the design may evolve, although formal controls are placed on any changes to issued design documents. This might mean that interim change may occur within particular aspect of the works, which, when finalised, are formally reviewed and incorporated into the design. Design chill also has the effect of reducing possible diversions into development that over-engineers the design or introduces additional “benefits” that were not foreseen at the start of the work. Parts of a design can be chilled whilst permitting other aspects to continue to develop; for example, the civil aspects may be chilled, allowing M&E design to continue in the full knowledge that there will be no change to the structure. |
For more information see: Design freeze: a quality perspective.
[edit] Related articles on Designing Buildings
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.