Difference between cost plan and budget
It is important not to confuse cost plans and budgets.
A budget is a statement of the amount of money available to spend over a period of time, or on a specific thing, such as a building. The budget is set by the client (although they make seek help to do this). It may include an outline plan for how that money will be spent, and a breakdown of the items it will be spent on. Budgets set a limit for expenditure and this can help determine what is affordable. They should be set as early as possible so that expectations can be managed. It is important that they are based on evidence and that they are realistic, rather than simply stating the amount of money available, or being a wild guess, because, once the budget is set in people's minds, it can be very difficult to change.
For more information see: Budget.
Cost plans are typically prepared by a cost consultant and provide an estimate of what the actual costs are likely to be. Cost plans evolve through the life of the project, developing in detail and accuracy as more information becomes available about the nature of the project. They can range from very early initial cost appraisals through to tender pricing documents and the final account. If the cost plan exceeds the budget, it may be necessary to reduce the cost or scope of the project.
For more information see: Cost plan.
[edit] Related articles on Designing Buildings
- Budget.
- Capital costs for construction projects.
- Construction costs.
- Cost control.
- Cost plans for construction projects.
- Cost management techniques used to monitor the cost of construction projects.
- Difference between collateral warranties and third party rights.
- Difference between preliminaries and preambles
- Elemental cost plan for design and construction.
- Final account.
- Outturn cost.
- Quantity surveyor.
- Tender pricing document.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.