[edit] Introduction
Engineering Recommendation G99, or EREC G99, was issued by the Energy Networks Association (ENA) in July 2018 and came into effect on 27 April 2019. It applies to organisations involved in developing generation projects that are connected to the grid. It also affects how different types or configurations of equipment must comply with the requirements.
EREC G99 was published by the ENA to replace EREC G59. After 27 April 2019, organisations were longer legally permitted to connect certain types of power generation equipment that was solely compliant with G59.
[edit] Changes brought about by EREC 99
EREC 99 established more stringent operating parameters for all new generation equipment 1MW (or larger) that would be connected to public distribution networks of licensed Distribution Network Operators (DNOs). It also changed the application process for this type of equipment and put new compliance and commissioning requirements in place.
Under EREC G99, this type of equipment must provide frequency response in either Limited Frequency Sensitive Mode (LFSM) or Frequency Sensitive Mode (FSM) to control active power output in response to frequency changes on the grid.
Generators over 1MW must also include:
- Fault ride through to keep them connected when there are significant voltage depressions due to faults on the grid.
- Fast fault current injection to support the system during a fault by quickly injecting reactive current in order to keep the grid voltage from dropping too low.
- Voltage control systems that can inject or absorb reactive power into the grid to control voltage.
- Enhanced variable reactive power capabilities.
- Testing and protection capabilities previously handled by large grid code compliant power stations.
[edit] Related articles on Designing Buildings
- Microgeneration for buildings
- Power generation
- Power supply.
- Smoothing the path to net zero.
- The future of UK power generation.
[edit] External resources
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.