Flood risk assessment
[edit] Introduction
A flood risk assessment is required for most developments within one of the flood zones.
This includes developments that are:
- In flood zone 2 or 3 including minor development and change of use.
- More than 1 hectare (ha) in flood zone 1.
- Less than 1 ha in flood zone 1, including a change of use in development type to a more vulnerable class (for example from commercial to residential), where they could be affected by sources of flooding other than rivers and the sea (for example surface water drains, reservoirs).
- In an area within flood zone 1 which has critical drainage problems as notified by the Environment Agency.
It is not necessary to carry out a flood risk assessment for a development that is less than 1 ha in flood zone 1 unless it could be affected by sources of flooding other than rivers and the sea, for example surface water drains.
You can find out more at: https://www.gov.uk/guidance/flood-risk-assessment-for-planning-applications
[edit] Home Quality Mark
For the purposes of the Home Quality Mark, a Flood Risk Assessment (FRA) or Flood Consequence Assessment (FCA) is defined as:
A study to assess the risk of a site flooding, and to assess the impact that any changes or development on the site will have on flood risk to the site and elsewhere. A FRA should be prepared according to relevant planning policy and technical guidance documents. The FRA must account for future climate change and detail any necessary adaptation measures where or if required. Where more than five years have passed since the FRA was carried out, evidence would be required to demonstrate that the basis of the FRA has not changed in that time. |
Ref Home Quality Mark One, Technical Manual SD239, England, Scotland & Wales, published by BRE in 2018.
[edit] Related articles on Designing Buildings
- BREEAM Flood risk management.
- Building Research Establishment.
- Changing attitudes to property flood resilience in the UK
- Design flood event.
- Design flood level.
- Flood.
- Flood Risk Framework.
- Home Quality Mark.
- Flood and Water Management Act.
- Flood plain
- Flood risk
- Flood risk management plan
- Flood zone
- Flood defences
- Planning for floods.
- Property flood resilience
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.