Form of tender
A tender is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services. An invitation to tender might be issued for a range of contracts, including: equipment supply, the main construction contract (perhaps including design by the contractor), demolition, enabling works, and so on.
An invitation to tender might include:
- A letter of invitation to tender.
- The form of tender.
- Preliminaries.
- The form of contract.
- A tender pricing document.
- A drawing schedule.
- Design drawings.
- Specifications.
The form of tender is prepared by the client or their consultants and completed and signed by the tenderer. It is a formal acknowledgement that the tenderer understands and accepts the terms of conditions of the tender documents and any other requirements that are stipulated.
Items that might be appear on a form of tender could include:
- Latest return time and date.
- Date, name and address.
- Tender reference number.
- The price for which they are to do the works and any adjustments prices that have been agreed should the scope of the work or period of time change (or a reference to documents providing this information).
- The date until which the price remains valid.
- The period of time that is allocated for the works, or an actual completion date if required.
- Acceptance of terms and conditions.
- Confirmation of the country’s law that will govern the contract.
- References to other documents containing information.
- Any qualifications that apply.
- Who will bear the costs of preparing the tender.
- Any alternative proposals (or a reference to documents providing this information).
- Confirmation of the tender being genuine and bona fide.
- Signature and tenderer details.
Some of these items may be filled out by the client or their consultants in advance, so that the tenderer only has to agree and sign.
[edit] Related articles on Designing Buildings Wiki
- Bid strategies.
- Common mistakes in construction tenders.
- Contract documents for construction.
- Construction contract.
- Contract conditions.
- Contract engrossment.
- Contract execution.
- Contractual documents.
- Negotiated contract.
- Schedules of work.
- Specifications.
- Tender.
- Tender documents.
- Tender negotiations.
- Tender processes.
- Tender return slip.
- Tender settlement meeting.
- Tender submission.
- Things to avoid when tendering.
- Variant bid.
[edit] External references
- Felp - Sample form tender
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.