Hot water safety
Contents |
[edit] Introduction
Hot water is considered an essential building service. The two components of a typical hot water system are:
- The central heating system which supplies hot water to radiators located around a building.
- Domestic hot water supplied to taps and sometimes to appliances.
The water and pipework used for these two systems are not mixed, although both share some of the same components.
[edit] Hot water safety under Section G3 of Approved Document G
Section G3 of Approved Document G defines ‘domestic hot water’ as water that has been heated for cooking, food preparation, personal washing or cleaning purposes. Under Approved Document G, the “suitable installation for the provision of heated wholesome water or heated softened wholesome water” is required.
Section G3 provides specific guidance regarding hot water safety for sanitaryware (including washbasins, sinks, baths, showers and bidets) and other water storage systems (including cisterns or other water supply vessels). Under Section G3, systems should incorporate precautions to:
- Prevent the temperature of the water stored in the vessel at any time exceeding 100C.
- Ensure that any discharge from safety devices is safely conveyed to where it is visible but will not cause a danger to persons in or about the building.
Furthermore, the hot water supply to any fixed bath must be so designed and installed as to incorporate measures to ensure that the temperature of the water that can be delivered to that bath does not exceed 48C.
Section G3 provides specific information on additional areas, including
Guidance:
- Performance
- General
- Provision of hot water supply
Design and installation of directly or indirectly heated hot water storage systems:
- General
- Vented hot water storage systems
- Unvented hot water storage systems – all systems
- Unvented hot water storage systems – systems up to 500 litres capacity and 45kW power input
- Unvented hot water storage systems – systems over 500 litres capacity or over 45kW power input
Safety devices:
- Non-self-resetting energy cut-outs
- Temperature and pressure relief devices
Discharge pipes from safety devices:
Prevention of excessive temperatures
Prevention of scalding
Commissioning of fixed building services
Notice of completion of commissioning
[edit] Further guidance
In addition to the information in Approved Document G, further guidance for hot water storage system design and installation can be found in three British Standards Institution (BSI) documents:
- BS EN 806-5:2012 Specifications for installations inside buildings conveying water for human consumption. Operation and maintenance.
- BS 8558:2015 Guide to the design, installation, testing and maintenance of services supplying water for domestic use within buildings and their curtilages.
- BS EN 12897:2006 Water supply.
[edit] Related articles on Designing Buildings
- A guide to installing thermostatic mixing valves: what, why and how.
- Approved Document G.
- Building services.
- Hot water.
- Hot water safety in health and social care settings.
- Plumbing.
- Stagnation point.
- Tap.
- Water heating.
[edit] External resources
- BSI, BS EN 806-5:2012 Specifications for installations inside buildings conveying water for human consumption. Operation and maintenance.
- BSI, BS 8558:2015 Guide to the design, installation, testing and maintenance of services supplying water for domestic use within buildings and their curtilages.
- BSI, BS EN 12897:2006 Water supply.
- Gov.uk, Approved Document G.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.