Post project review of construction projects
A post project review may begin during the defects liability period, when the client first occupies the development (now called the 'rectification period' in Joint Contracts Tribunal (JCT) contracts).
A post project review is undertaken to evaluate the effectiveness and efficiency of the project delivery process. To undertake a post project review, it is important to seek the views of contractors, designers, suppliers and the client about how well the project was managed.
This may include assessments of how well the delivery of the project performed against key performance indicators such as:
- The quality of briefing documents.
- The effectiveness of communications.
- The performance of the entire project team.
- Quality issues.
- Health and safety issues.
- Certification.
- Variations.
- Claims and disputes.
- Collaborative practices.
An evaluation can then be made of what lessons can be learned from the approach taken and a lessons learned report prepared.
A wider 'post occupancy evaluation' may comprise two studies:
- A post project review to evaluate the project delivery process.
- An assessment of performance in use, to assess the extent to which business and design objectives have been satisfied, which may not begin until 6 to 12 months after occupation, as operations may not be properly established before then.
See Post occupancy evaluation and Performance in use for more information.
NB When the development is first occupied by the client, it is important to visit the site immediately to identify any issues that need to be addressed quickly. It can be beneficial to establish a help-desk and rapid response team to resolve issues as they arise (See articles on occupation and migration strategy).
[edit] Related articles on Designing Buildings Wiki
- BREEAM.
- Building performance metrics.
- Defects liability period.
- End of contract report.
- Energy performance certificates.
- Extended aftercare.
- Initial aftercare.
- OGC Gateway Review 5: Operations review & benefits realisation (or benefits evaluation)
- Migration strategy.
- Performance in use.
- Performance of exemplar buildings in use: Bridging the performance gap FB 78.
- Post occupancy evaluation (repeats some of the text in this article).
- Post opening project evaluation.
- Soft landings.
- Value added.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.