Relief well
Contents |
[edit] Introduction
The International Levee Handbook, published by CIRIA in 2013, defines a relief well in water and flood management terms as: 'A vertically installed well consisting of a well screen surrounded by a filter material designed to prevent in-wash of foundation materials into the well. Relief wells are used extensively to relieve excess hydrostatic pressure in impervious foundation strata overlain by more impervious top strata, conditions that often exist landside of levees and downstream of dams and various hydraulic structures.'
Relief wells are also used in the fossil fuel industry as a control measure for natural gas and petroleum drilling.
[edit] History
The use of relief wells goes back to the early 1900s. They were initially used in the fossil fuel sector to manage well pressure. In the 1940s, relief wells were used to manage water pressure associated with dams. The technique was later adopted as a precautionary measure during construction to control water tables that could destabilise the ground..
[edit] Maintenance
The US Army Corps of Engineers has incorporated relief wells into the design and construction of several dam projects since the 1940s. Based on its experience, the organisation has observed that the life cycle of relief wells includes a slow but steady decline in pump efficiency after five years of operation. Regular maintenance and pump testing is required.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.