Residual risk in building development
The development of buildings is carried out in several phases, all involving hazard, uncertainty and risk. Risks which may occur on construction projects can sometimes be designed out or avoided. Remaining risks may be:
- Transferred to the contractor.
- Shared by the employer and contractor.
- Retained by the employer.
According to NRM2: Detailed measurement for building works, the term ‘residual risk’, or ‘retained risk’ refers to risks retained by the employer, that is, unexpected expenditure arising from risks that materialise, which are retained by the employer rather than being transferred to the contractor.
The employer may ask the contractor to provide a price for taking on a risk themselves before deciding to retain a risk.
Residual risks retained and managed by the employer or their project team are described as the employer’s residual risk exposure. Risk allowances should be included in cost plan to provide for this exposure.
Government Functional Standard, GovS 002: Project delivery; portfolio, programme and project management, Version: 2.0, published on 15 July 2021 by HM Government, defines a residual risk as: ‘The risk remaining after the risk response has been applied.’
[edit] Related articles on Designing Buildings
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.