Risk assessments and method statements RAMS
Contents |
[edit] Introduction
RAMS are Risk Assessments and Method Statements.
[edit] Risk assessments
The Construction (Design and Management) Regulations (CDM Regulations) are intended to ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who build, use and maintain structures is reduced.
They require that as the design progresses, risks are identified and eliminated and residual risks are reduced and managed and that designers, principal designers, principal contractors and contractors take account of the 'principles of prevention' in carrying out their duties, which in general terms are:
(a) Avoid risks where possible.
(b) Evaluate those risks that cannot be avoided.
(c) Put in place proportionate measures that control them at source.
Whilst the specific process of preparing a formal risk assessment is not a requirement of the CDM regulations, regulation 3(6)(a) of the Management of Health and Safety at Work Regulations does require that risks are controlled in the workplace, including construction sites. This involves thinking about what might cause harm to people and deciding what steps to take to prevent that harm. Where an employer employs five or more people, the significant findings of risk assessments must be recorded.
For more information, see Risk assessments.
[edit] Method statements
Method statements are widely used in construction as a means of controlling specific health and safety risks that have been identified (perhaps following the preparation of a risk assessment) such as; lifting operations, demolition or dismantling, working at height, installing equipment, and the use of plant.
A method statement helps manage the work and ensures that the necessary precautions have been communicated to those involved.
Like risk assessments, producing written method statements is not an explicit requirement of the CDM Regulations, however they are identified by the Health and Safety Executive as one way of satisfying the requirements of the regulations and as an effective means of assessing risks, managing risks, collecting workers’ views and briefing workers.
Method statements need be no longer than is necessary for them to be effective. They are for the benefit of those carrying out the work and so should be clear, should not be overcomplicated and should be illustrated where necessary.
For more information, see Method statements
[edit] RAMS
So, generally a risk assessment is undertaken to identify (and where possible eliminate) risks, and then a method statement is prepared to control residual risks.
They are sometimes described together as 'RAMS'. RAMS may be required by third parties to demonstrate that health and safety has been properly considered and that the requirements of the CDM regulations have been satisfied. For example, a contractor may require submission of RAMS form sub-contractors, a landlord may require submission of RAMS from tenants proposing to carry out works to a property, or a client may require submission of RAMS from contractors operating on their premises.
[edit] Related articles on Designing Buildings
- As Low As Reasonably Practicable (ALARP).
- CDM.
- Contractor.
- Deleterious materials.
- Demolition.
- Design risk management (DRM)
- Health and safety.
- How to write a method statement.
- Method statements.
- Permit to work.
- Principal contractor.
- Project execution plan.
- Risk assessment.
- Risk feedback.
- Site records and registers.
- Temporary works.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.
Comments
Excellent, very helpful. I just bookmarked the website.