Specific performance in construction contracts
Specific performance is an equitable remedy available for breach of contract which requires the contract breaker to fulfil their contractual obligations.
Specific performance is not a right, but may be granted at the court’s discretion (as opposed to damages, a contractual remedy available as of right if the claimant proves its loss) in addition to, or instead of damages.
So, for example, where a binding contractual obligation has been entered into to give collateral warranties, in the event of failure to give the warranty, the other party to the principal contract could apply to the Court for an order of specific performance requiring the warranty to be entered into. For such an application to be successful, the wording of the contractual obligation will have to be clear and unambiguous.
In the case of Liberty Mercian Limited v Cuddy Civil Engineering Limited and others, Mr Justice Ramsey decided that whilst the unperformed primary obligations arising from a contract cease on termination, ancillary rights or obligations which have accrued from the performance of the contract, for example, the provision of performance bonds or warranties, survive termination. These are continuing obligations which must be honoured despite the fact that the main contract has come to an end. The Claimant was therefore entitled to the remedy of specific performance to enforce the delivery of executed warranties.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.