Time and material contract (T&M)
In the United States, a time and material contract (T&M) is a type of construction contract that commits the client to pay the contractor based upon the time spent on the works, the materials used, as well as a mark-up for profit. In the UK, this type of contract is known as a cost reimbursable contract or cost plus.
This differs from a fixed price contract which commits the client to pay the contractor a lump sum fee for fulfilling the contract regardless of the amount on labour, materials, and so on used. A T&M contract is typically used on projects where it is difficult to describe the extent of the works required accurately, or where specifications and requirements are likely to change as the project progresses.
The main items that can be included in a T&M contract are:
- Labour rates: The amount that will be charged for the workforce, which may also include insurance, taxes, and so on.
- Material mark-up: It is usual for the client to be charged the retail price for materials and for a mark-up to be added by the contractor if they have a pre-agreed wholesale price with the supplier.
- Not-to-exceed: A guaranteed maximum price which places an upper limit on what the client can be charged by the contractor.
The advantages of using a T&M contract include:
- It provides the client with cost transparency and allows them to verify invoices and timesheets to ensure the costs are correct.
- It allows for greater flexibility in the extent of the works required.
- It allows works to progress even when there is no definitive plan for how it will be completed.
- It saves time in the initial estimating process which otherwise has to be done to a much higher level of detail and accuracy.
- Although there is generally a limit on their profit, the contractor can proceed knowing they are going to recover expenses with some profit, and so they can avoiding cost-cutting.
The disadvantages of using a T&M contract include:
- It can prove more risky for the client to proceed without a clear understanding of the final cost.
- It can increase the likelihood of disputes arising.
- Errors or inaccurate estimates can leave them with a low profit that may not be deemed worthwhile.
- It can necessitate more involvement from the client to ensure the contractor is motivated to progressing the works on time and within budget.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.