Undefined provisional sum
A provisional sum is an allowance (or best guess), usually estimated by a cost consultant, that is inserted into tender documents for a specific element of the works that is not yet defined in enough detail for tenderers to accurately price.
A provisional sum can be categorised as ‘defined’ or ‘undefined’.
Undefined provisional sums are less well described as they refer to work which is not completely designed. As such, the contractor cannot be expected to make allowance for them in their programming, planning and pricing preliminaries. This means the contractor may be entitled to an extension of time and/or additional payments when the actual works are undertaken.
An example of an undefined provisional sum might be work required below an existing structure, where the ground conditions, and so the extent of work required, cannot be determined until the structure is demolished and the ground opened up.
With undefined provisional sums, the client typically bears the price and scheduling risks.
Defined provisional sums are those which have been described in sufficient detail that the contractor is expected to have made allowance for them in their programming, planning and pricing preliminaries.
[edit] Related articles on Designing Buildings
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.