Vicarious performance
'Vicarious performance' refers to the carrying out of contractual obligations by a person who is not party to a contract, usually by sub-contract or assignment. So, for example, performance by a sub-contractor constitutes vicarious performance on behalf of the main contractor, who remains fully responsible for the work, except where the main contract provides otherwise.
Whether the contractor is allowed to delegate vicarious performance of either all or some of their obligations to a third party will depend on the terms of the contract.
Vicarious performance of the work and whether it is permitted is usually decided based upon whether it either:
Where the work is of a non-specialist nature, the right of the contractor to employ a sub-contractor is normally implied.
British Waggon Co. & Parkgate Waggon Co. v. Lea (1880), is often viewed internationally as being the authoritative case. The original contractor (Parkgate) contracted to keep railway carriages in repair for Lea & Co. over a number of years. The original contract did not call for the repairs being necessarily effected by the Parkgate company itself, but could be undertaken by any company capable of completing the works to a similar standard. The Parkgate Company had arranged with the British Waggon company that the latter should execute the repairs. Therefore, on liquidation of Parkgate, the benefit and burden of the contract was assigned to British Waggon. Lea could not refuse performance despite the assignment.
Cockburn CJ stated: 'All that the hirers, the defendants, cared for in this stipulation was the wagons should be kept in repair; it was indifferent to them by whom the repairs should be done. Thus if, without going into liquidation, or assigning these contracts, the company entered into a contract with a competent party to do the repairs, and so procured them to be done, we cannot think that this would have been a departure from the terms of the contract to keep the wagons in repair.'
The ruling on this case was based on the fact that Parkgate was originally bound by the contract to undertake the repairs, thereby producing a result (not necessarily by its own efforts) but, if it wanted to, by vicarious performance through a sub-contractor or otherwise. By getting the repairs satisfactorily completed by a third party, Parkgate had discharged its obligations of repair under the contract.
NB: The British Waggon ruling may not apply where the contractor has been chosen for their specialist skills, reputation and ability to perform complex operations efficiently.
The contractor's liability for the defaults of the sub-contractor may arise in either tort or in contract.
[edit] Related articles on Designing Buildings Wiki
- Assignment.
- Back-to-back provisions in construction contracts.
- Common law.
- Construction contracts.
- Contractor.
- Contractor vs supplier.
- Domestic sub-contractor.
- Named specialist work.
- Named sub-contractor.
- Nominated sub-contractor.
- Sub-contractor.
[edit] External references
- 'Construction Contract Law: The Essentials', ADRIAANSE, A., Palgrave MacMillan (2005)
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.