Wayleave
A wayleave is a contract between a the owner or occupier of land (the grantor) and a third party (the grantee) permitting the grantee to access privately-owned land to carry out works in return for some form of compensation.
Typically they are used to allow utilities companies to install cables, pipes, pylons or other equipment or apparatus on privately-owned land and giving them access to the site at reasonable times to be able to carry out inspections, alterations, renewal, removal, maintenance and repairs.
A wayleave is similar to an easement, but differs in that the easements are executed as deeds, are registered with the Land Registry and are permanently attached to the land in return for a one-off payment. This gives better security to the grantee, who may be prepared to pay more than for an easement than a wayleave, but an easement may impact on the long-term value of the land if the landowner chooses to sell or lease the land.
Wayleaves include termination clauses and are not permanent, however, questions have been raised about how straight-forward it is to terminate agreements, and some wayleaves are protected by statutory code powers.
Payments are generally annual, but can be made as a single lump-sum payment. A wayleave payment may consist of two parts, the owner’s payment and the occupier’s payment, and may include a contribution to the landowner’s or occupier’s legal costs. The grantee should commit to minimising any damage to the property and to make good or pay compensation where there is damage.
If it is the landowner that requires the service that is being installed, this may be dealt with under a customer service contract rather than a wayleave.
The complexity of wayleaves and the potential long-term impact on land means that both parties should seek legal advice before entering into an agreement.
[edit] Related articles on Designing Buildings
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.