Accepted programme
Within the NEC Engineering and Construction Contract (ECC), the ‘accepted programme’, is identified within the Contract Data.
The contractor prepares a programme for the works, which is then submitted to the project manager for their approval. If it is approved, this becomes the 'accepted programme'. The programme should be practicable and realistic, showing when the contractor intends to carry out each part of the works and identifying the resource they intend to use. Ref. NEC Dictionary.
The contract may also require that a revised programme is prepared regularly, setting out the sequence of activities, progress, and the effect of compensation events. This must then be submitted to the project manager, and if accepted, this becomes the accepted programme, sometimes referred to as the updated programme. The final updated programme will show the as-built programme.
Within the ECC, the ‘activity schedule’ allocates a price to each activity undertaken during the works. This simplifies the administration of the interim payment process. The accepted programme shows how the activities on the activity schedule are programmed. The accepted programme and the activity schedule need not show exactly the same activities, but there should be correlation between them, and they should be kept up to date.
Without an accepted programme the contract cannot be administered properly. Under such circumstances, 25% of payments can be withheld, and it is not possible to assess compensation events.
Accepting the programme does not discharge the contractor of any responsibility, it simply accepts that the programme is realistic and that it can be used to assess future changes. If the programme is not accepted by the project manager, reasons for not accepting it must be given.
Reasons might include:
- It is not practical.
- It does not show required information.
- It does not properly represent the actual programme for activities.
- It does not show the full works.
Failure to accept or reject a programme may constitute a compensation event.
NEC4 introduces the new concept of ‘treated acceptance’, by which the project manager has a specified period of time to notify the contractor whether the programme has been accepted or not. If they fail to notify the contractor within this period, the programme is deemed to be accepted.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Baseline programme.
- Compensation event.
- Contract conditions.
- Contract data.
- Contractor's master programme.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Early warning notice.
- Key dates.
- NEC contract change management systems.
- NEC early contractor involvement.
- NEC3.
- Programme.
- Programme for building design and construction.
- Programme narrative.
- Progress in construction.
- Short period programme.
- Tender works programme.
- Time Risk Allowance TRA.
- Works information.
- Z clauses.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.