Calderbank offer
A Calderbank offer is a settlement offer made on a "without prejudice save as to costs" basis.
It is an approach used to settle a dispute for a lower amount and avoid going to a court trial. It puts one side on notice that if the dispute goes before a court, and the outcome is worse than the Calderbank offer being made, the party making the Calderbank offer is entitled to higher recovery court costs, the fact the offer has been made may also be taken into account when considering the costs awarded.
Important constituents of such an offer are:
- It must be left open for acceptance for 21 days.
- It must offer to pay the other party’s reasonable costs incurred up to the point of acceptance if accepted within 21 days. Thereafter, acceptance being subject to the offeror’s costs incurred after the expiry of the 21 days being paid.
- It must say what is the position as to interest. Normally interest is included.
- It must say whether any counterclaim is taken into account in the offer.
It is named after the case Calderbank v. Calderbank in 1975. Mrs Calderbank before the dispute proceeded to the courts, showed she had a willingness to settle the dispute. If Mr Calderbank had accepted the offer made to him before the trial, he would have been in a better position because the outcome was less favourable to him than Mrs Calderbank’s earlier offer, and then neither would have had to go to court. The court ruled that Mrs Calderbank was entitled to her costs as from the date that she made her willingness to settle known.
It is an alternative to a Part 36 offer, which is a written offer to settle with a period of not less than 21 days during which it can be accepted. If it is not accepted in the stated period and the other party does not beat that offer then there will be costs consequences.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Alternative Dispute Resolution legislation.
- Arbitration Act.
- Arbitration panel.
- Arbitration v Adjudication.
- Arbitration in the construction industry
- Breach of contract.
- Causes of construction disputes.
- Conciliation.
- Construction Industry Model Arbitration Rules CIMAR.
- Contract claims.
- Dispute resolution.
- Dispute resolution boards.
- Dispute resolution procedure.
- Evaluation of claims.
- Expert determination.
- Expert evaluation.
- Housing Grants, Construction and Regeneration Act.
- How does arbitration work?
- How to become an arbitrator.
- Joinder.
- Mediation.
- Part 36 offer
- Pay now argue later.
- Pendulum arbitration.
- Provisional relief.
- The role of the mediator.
- Scheme for Construction Contracts.
- Without prejudice.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.