Functional indexation
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM3: Order of cost estimating and cost planning for building maintenance works:
The term ‘functional condition indexation’ (FCI) refers to:
‘…the ratio of the functional cost estimate of predicted life cycle major repairs or replacements (identified by a condition and Remaining life assessment) to the Capitalised replacement value or rebuild costs, expressed over an agreed period of analysis (e.g. a banding of years such as 1, 2 to 3, 4 to 5, 6 to 10 or 11+).’
The term ‘functional maintenance indexation’ (FMI) refers to:
‘…the ratio of the functional unit cost estimate of annualised maintenance (i.e. planned, reactive and proactive maintenance) to the Capital replacement value (CRV) or rebuild costs, expressed over an agreed period of analysis (e.g. a banding of years such as 1, 2 to 3, 4 to 5, 6 to 10 or 11+).’
And the term 'functional re-investment indexation' (FRI) refers to:
‘…the ratio of the functional cost of major repairs or replacements (identified by a condition and other form of asset assessment) to the Capital replacement value (CRV) or rebuild costs, expressed over an agreed period of analysis (e.g. a banding of years such as 1, 2 to 3, 4 to 5, 6 to 10 or 11+).’
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.