Order of cost estimate
The purpose of an order of cost estimate is to establish affordability of a proposed development for a client.
Methods for preparing order of cost estimates are set out in the New Rules of Measurement:
- NRM 1: Order of cost estimating and cost planning for capital building works
- NRM 3: Order of cost estimating and cost planning for building maintenance works.
NRM1 defines an order of cost estimate as; '...the determination of possible cost of a building(s) early in design stage in relation to the employer’s fundamental requirements. This takes place prior to preparation of a full set of working drawings or bills of quantities and forms the initial build-up to the cost planning process.'
A wide range of information may be required from the parties to the project to prepare an order of cost estimate:
From the employer:
- Location and availability of site.
- Statement of building use and size.
- Any refurbishment requirements.
- Initial project/design brief.
- Enabling works details.
- Draft programme.
- Site conditions.
- Budget/cash flow constraints.
- Construction procurement options.
- Life span of the proposed building.
From the architect:
- Design study sketches or drawings.
- Schedules of areas.
- Legislative constraints.
- Initial risk register.
Information can also be provided by the services engineer, structural engineer, and other consultants if these have been appointed.
The key constituents of an order of cost estimate are typically:
- Facilitating works.
- Building works.
- Contractor’s preliminaries.
- Contractor’s overheads and profit.
- Construction cost.
- Fees.
- Other development/project costs.
- Risk allowances.
- Inflation.
Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines an order of cost estimate as: ‘An estimate based on benchmark data for a similar type of project based on a defined brief.’
[edit] Related articles on Designing Buildings
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.