Work package bill of quantities
A bill of quantities (sometimes referred to as a 'BoQ' or 'BQ') is a document, typically prepared by a cost consultant (often a quantity surveyor), that provides measured quantities of the items of work identified by the drawings and specifications in the tender documentation for a project. It is issued to tenderers to allow them to prepare a price for carrying out the works.
According to NRM2, RICS new rules of measurement, Detailed measurement for building work, there are three main breakdown structures for bill of quantities:
- Elemental bill of quantities.
- Work package bill of quantities.
- Work section bill of quantities.
The work package breakdown structure undertakes measurement and description divided into employer, quantity surveyor or contractor defined work packages (based either on a specific-trade, or a single package comprising a number of different trades). This structure may be preferred by contractors for procuring from their supply chain.
NRM 2 suggests that a typical breakdown structure for a discrete work package might be:
- Bill No. 1: Main contractor’s preliminaries.
- Bill No. 2: Intrusive investigations.
- Bill No. 3: Demolition works.
- Bill No. 4: Groundworks.
- Bill No. 5: Piling.
- Bill No. 6: Concrete works.
- Bill No. 7: Roof coverings and roof drainage.
- Bill No. 8: External and internal structural walls.
- Bill No. 9: Cladding.
- Bill No. 10: Windows and external doors.
- Bill No. 11: Mastic.
- Bill No. 12: Non-structural walls and partitions.
- Bill No. 13: Joinery.
- Bill No. 14: Suspended ceilings.
- Bill No. 15: Architectural metalwork.
- Bill No. 16: Tiling.
- Bill No. 17: Painting and decorating.
- Bill No. 18: Floor coverings.
- Bill No. 19: Fittings, furnishings and equipment.
- Bill No. 20: Combined mechanical and electrical engineering services.
- Bill No. 21: Lifts and escalators.
- Bill No. 22: Facade access equipment.
- Bill No. 23: External works and drainage.
- Bill No. 24: Risks.
- Bill No. 25: Provisional sums.
- Bill No. 26: Credits.
- Bill No. 27: Daywork (Provisional).
[edit] Related articles on Designing Buildings
- Advantages of a bill of quantities.
- Approximate bill of quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Facade access equipment.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- NRM1.
- NRM2.
- NRM3.
- Schedule of rates.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender.
- Tender documentation.
- Tender pricing document.
- Types of bill of quantities.
- Uniclass.
- Work section bill of quantities.
Featured articles and news
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.